Rasmussen Mechanical Services recently completed the demolition and replacement of a low-pressure steam boiler system with the installation of a new Peerless PER211A05SPRKSN Cast Iron Sectional Boiler. This project brought major upgrades to the steam infrastructure, ensuring long-term performance and reliability.
Scope of Work Included:
-
Demolition of the existing boiler and removal of outdated components
-
Installation of a new Peerless PER211A05SPRKSN low-pressure steam boiler
-
New condensate return/makeup water tank with duplex pump configuration for redundancy and efficiency
-
Reinstallation of boiler room piping, including:
-
New gas piping from the existing shut-off valve to the boiler
-
New steam header piping, reconfigured from the north end union to the boiler for proper system design
-
New condensate piping throughout the boiler room
-
-
New insulation applied to all new piping to improve efficiency and safety
-
System testing and verification to ensure optimal functionality and safe boiler operation