Processing Plant

Project

3,600 BHP Boiler Install

Location

Aberdeen, SD

More Information

  • Boiler Repair
  • Burner Services
  • Mechanical Construction

Project Details

A local processing plant had plans to increase production at their facility, and as a result, also needed to increase steam capacity.  Rasmussen Mechanical  was contracted to install a new 3,600 BHP Cleaver Brooks watertube boiler with Autoflame controls and a duel fuel Limpsfield Burner (Natural Gas and Fuel Oil as back-up).

As part of this project, Rasmussen Mechanical upgraded controls on an existing boiler and installed a stack economizer on the new system to assist in energy reduction. An MAU was also installed to provide tempered combustion air when the ambient temperature is below 45 degrees F.