Warren Distribution

Project

Tank Realignment

Date Completed

July 2017

Location

Council Bluffs, Iowa

More Information

  • Design Build
  • Mechanical Construction

Project Details

Partners often approach us to help improve their facility’s production efficiencies and operations. The purpose of this project was to boost the versatility in the plant’s process piping.

The new design gives more control to plant operators because of the modi cations made to the piping manifolds and system pumps.

The project included 3” and 6” stainless steel process piping, 3” and 4” piggable piping and valves, a new mechanical mezzanine, and the installation of 13 pumps that ranged from 15-30 horse power.

  • 6 month project.
  • New process piping was designed in coordination with Warren Distribution.
  • Increased control in plant operations.
  • Designed and installation of mechanical mezzanine.
  • 0 injuries.